Challenge
- A client approached us with a fully microfluidic design, aggressive development timelines, and stringent cost targets.
- The client would have burned through 80% of their budget before realizing they wouldn’t reach their cost targets.
Solution
- Assessed their existing design and identified its inability to meet cost and timeline goals.
- Developed a liquid handler-based approach tailored to their workflow and functional requirements.
Outcome
- Worked with Arete to develop new consumable that was within their cost target in 6 months and got them back on track to meet their launch target.
- Achieved RUO (Research Use Only) launch in under a year.
- Delivered within budget, meeting final cost targets and functional assay needs.